On October 13, 2026, the Ho Chi Minh City Department of Finance issued Official Letter 30060/STC-KTĐN regarding the submission of periodic investment reports (for non-budgetary investment capital implemented for projects located outside industrial parks, export processing zones, high-tech zones, and free trade zones). This article provides guidance on where to submit periodic investment reports, required documents, submission deadlines, and other notes on reporting obligations during the implementation of investment projects.
Where and when should I submit the report?
Project implementation status report
| Submission location |
Online at National Investment Information System: fdi.mof.gov.vn Use the account that has been provided. |
| Duration | 🔸 Quarterly report: before the 10th day of the first month of the following quarter. 🔸 Annual Report: before March 31st, the following year. |
| Form | Forms I.3.1 to I.3.5 issued together with Circular 55 / 2026 / TT-BTC May 15, 2026. |
Investment monitoring and evaluation report
| Submission location |
Online at The Ministry of Finance's investment monitoring and evaluation information system: giamsatdautuquocgia.mof.gov.vn Use the account that has been provided. |
| Duration | 🔸 Quarterly report: before the 10th day of the first month of the following quarter. 🔸 Six-month report: before 10-07; data covers the period from January 01st to June 01th of the reporting year. See the FAQ for more information regarding the 30-month submission period. 🔸 Annual Report: before 10-02, the following year; data covers the period from January 01st to December 01st of the reporting year. |
| Form | Form number 13 — Quarterly and annual monitoring and evaluating report on the implementation of investment projects, issued herewith Circular 44 / 2026 / TT-BTC; including the implementation status and the status of exploitation & operation of the investment project. |
⚠️ Note regarding digital signatures: Organizations and individuals using the System must use digital signatures as prescribed when submitting reports (Clause 7, Article 99 of Decree 96/2026/ND-CP and point b, clause 2, Article 3 of Circular 44 / 2026 / TT-BTC).
Some notes on reporting during project implementation.
In addition to the regular report, Section 3.3 of Official Letter 30060/STC-KTĐN also provides guidance on reporting and updating obligations related to project adjustment, completion, and operation:
- Updates on adjustments and unexpected events: Update information and data on the system no later than 07 working days from the date the competent authority approves the adjustment or unforeseen circumstances, such as adjustments to investment policies, projects, designs, contracts, or contractor selection plans.
- Before adjusting the investment project: Conduct a monitoring and evaluation report before making any project adjustments.
- Upon completion of the project: Update project settlement information within 07 working days from the date of approval and prepare a final evaluation report.
- During the exploitation and operation phase: Periodically (quarterly and annually) update information and data, and prepare monitoring and evaluation reports on the exploitation and operation on the System.
Detailed forms are available in Form 13, 15, 16, 17 and 18 issued together with Circular 44 / 2026 / TT-BTC; choose the form that best suits the content and stage of the project.
Q&A
Do foreign-invested enterprises that do not have an Investment Registration Certificate (IRC) have to submit these reports?
Reporting obligations associated with investment projects: The 2025 Investment Law mandates that investors and economic organizations implementing investment projects report quarterly and annually, and Circular 30060 is also sent to investors and economic organizations currently implementing projects in the area.
In response to a business with 49% foreign capital but without an Investment Registration Certificate, the Ministry of Finance determined that this business should follow the investment procedures of a domestic investor and suggested coordination with the investment registration agency and the local supervisory unit. The response did not conclude that the business was exempt from reporting requirements; therefore, confirmation with the Department of Finance should be obtained before the submission deadline.
Sources: Response from the Ministry of Finance dated [date] 21 October 2026; Clause 2, Article 47 of the 2025 Investment Law.
If I have already submitted the report on the Investment Monitoring and Evaluation System, do I need to submit it again on fdi.mof.gov.vn?
✅ Yes, These are two separate reporting regimes: the investment monitoring and evaluation report (Form No. 13, Circular 44/2026/TT-BTC) and the project implementation report according to Decree 96/2026/ND-CP (form in Circular 55/2026/TT-BTC). The Ministry of Finance instructs investors to fully implement both.
Reports on the Monitoring System replace paper reports and must be digitally signed; the Ministry also encourages businesses to attach scanned copies of signed paper reports.
Sources: Response from the Ministry of Finance dated [date] 19 October 2026.
Article 7 of Circular 44/2026/TT-BTC stipulates that investors only need to submit quarterly and annual reports. So, is it necessary to submit a semi-annual report?
According to the Ministry of Finance's guidelines, investors update data and prepare quarterly and annual reports on the Investment Monitoring and Evaluation Information System. Based on the quarterly data updates, the management agency can proactively compile data on the investment situation for the first six months of the year.
Businesses need to coordinate with the investment registration authority and the local investment monitoring and evaluation focal unit to implement data updating and periodic reporting. This guideline does not assert the abolition of the six-month reporting obligation or exemption from separate submission in all cases.
Sources: Response from the Ministry of Finance dated [date] 20 October 2026.
What steps should be taken on the system after a project has just received investment approval or an investment registration certificate?
Within 07 working days From the date of approval of the investment policy (and simultaneous approval of the investor), selection of the investor, or issuance of the Investment Registration Certificate, the investor shall update project information on the Investment Monitoring and Evaluation Information System, along with the decision, certificate, and related legal documents.
Source: Section II.3.2 of Official Letter 30060/STC-KTĐN; Article 7 of Circular 44/2026/TT-BTC.
How do I register for an account if I don't have a digital signature, and how long does it take?
Businesses register for accounts according to the instructions in Section II.2 of Official Letter 30060/STC-KTĐN. According to regulations, accounts are issued within one working day.
In fact, the Ministry of Finance stated that account issuance may take longer than the stipulated deadline due to the large number of applications, and that delays in account issuance will not be accepted as a reason for late report submission. Businesses should register early and not wait until the deadline.
Source: Section II.2 of Official Letter 30060/STC-KTĐN; Article 11 of Circular 44/2026/TT-BTC; Response from the Ministry of Finance dated [date] 17 July 2026.
What are the penalties for failing to submit or submitting reports late?
Official document 30060 cites Article 15 of Decree 122/2021/ND-CP. The following penalties apply to organizations:
- Investment monitoring and evaluation report that are failed to be submitted on time, lacking content, or failure to submit periodic reports: a fine of 20–30 million VND.
- Project implementation status report (Investment activity reporting regime) that are failed to be submitted or failed to be submitted on time: a fine of 30–50 million VND.
In addition, businesses are required to implement reporting procedures or supplement any missing information.
Source: Article 4, Clause 2, Article 15 of Decree 122/2021/ND-CP.